Installation Procedure
Togreen Infra RCC Precast Tanks
Togreen Infra Private Limited supplies precast tanks along with clear guidelines to ensure safe, fast, and leak‑proof installation at site.
Site Preparation and Excavation
- Mark the tank location and excavate the pit according to the tank dimensions, leaving at least 300 mm working clearance on all sides.
- Keep the pit dry and protected from surface water during excavation and installation.
- Where soil is poor or clayey, provide a PCC leveling course as recommended by the site engineer.
Base Preparation
- Provide a minimum 100 mm thick layer of well‑compacted sand or crusher dust as the bed.
- Level and compact this layer properly to form a uniform, firm base for full tank support.
- Check levels before lowering the tank to maintain correct inlet/outlet gradients.
Tank Placement
- Ensure adequate access (typically 3 m or more) for cranes or lifting equipment.
- Unload the tank using suitable lifting hooks, slings, and lower it slowly into the pit.
- Align the tank and connect inlet, outlet, and vent pipes using appropriate fittings.
Backfilling and Surface Works
- Backfill in layers using selected soil, sand, or crusher dust, compacting evenly on all sides.
- Protect the top slab from impact loads until backfilling is complete and area is stabilized.
- Complete final surface treatments ensuring access covers and manholes remain serviceable.
This installation procedure helps achieve stable support, proper pipe alignment, and long‑term watertight performance for Togreen Infra RCC precast water and sewage tanks.
Safe & Timely Delivery
Togreen Infra ensures your precast RCC tanks reach your site safely and on schedule. Our dedicated logistics team handles the entire delivery process with precision.
- Specialized transport vehicles for heavy precast elements
- Proper securing and padding to prevent transit damage
- On-time delivery coordination with site teams
- Pan-India delivery network
Professional On-Site Handling
Our team coordinates with crane operators and site personnel to ensure safe unloading and placement of precast tanks at the designated location.
- Skilled rigging and lifting operations
- Precise alignment and positioning
- Experienced supervision at every step
- Quality checks before final placement
Need Installation Support?
Contact us for professional guidance on your RCC tank installation.
Contact us